UNIVERSITY
LIBRARY CONSTRUCTION AND RENOVATION FACT SHEET

Design.
The addition was designed by The Architectural Group (TAG) of Mobile during
2000 and 2001.
Project
Management (External). Doster Construction Company.
Project
Schedule.
Work on the new addition began January 7, 2002 with the removal of the
trees and site work and should be completed in less than sixteen months,
or by June 2003. Foundation work should be completed by March 2002.
Description.
The
project consists of the construction of a new four-story, steel frame
and architectural pre-cast concrete and glass-clad addition to the existing
University Library. The addition should add approximately 54,000 sq.
ft. to the University Library. The project features concrete spread
footings, steel frame, cast-in-place concrete sheer walls, modified
bituminous membrane roofing, steel deck/concrete composite floor plates,
architectural pre-cast concrete exterior cladding, architectural curtain
wall glazing, conventional interior finishes, mechanical and electrical
systems connect to existing campus utilities.
Contracts
awarded.
-
Shell packages: site and concrete, masonry, pre-cast concrete, structural
steel, caulking and waterproofing, roofing, plumbing, elevators, curtain
wall (storefront and glazing)
-
Interior packages: electrical, doors and hardware, gypsum board assemblies,
ceilings, carpet and resilient flooring, ceramic tile, painting, heating
and air-conditioning, plaster, and fireproofing.
-
Demolition of the existing south entrance bridge
Features
and Benefits.
- Two
new entrances on the east and west at the parking lot level
- An
atrium to connect the new and existing libraries; it will split into
two story sections. The first atrium section will be about 22 feet tall
and the second about 25 feet tall. Catwalks across the atiums
top floors will connect the top floors to each other. Two new elevators
in the atrium area will be installed for the convenience of users..
- 54,000
additional sq. ft. of space for book stacks, offices, study rooms, staff
lounge, two elevators, three stairwells
- An
auditorium to seat over 100 persons
- Two
additional instructional classrooms, including a hands-on computer lab
for teaching database searching
- New
circulation desk at ground level
- The
Instructional Media Center (IMC) will be combined with the new Program
for the Enhancement of Teaching and Learning (PETAL) and occupy the
prime area on the ground (first) floor. The PETAL will be developed
to integrate technology into teaching and learning into the classroom,
particularly with respect to multi-media.
- Increase
natural light through glass curtain walls on the north, east and west
sides of the addition
- 24
new group study rooms
- Hundreds
of additional network connections throughout the addition, including
all group and individual study rooms
- A
new staff lounge
- Latest
fire protection and smoke evacuate system
Renovation
Project
Phase
one of renovation work will take place simultaneously with construction
beginning Spring semester 2002 and continue through 2003 and include the
following:
- asbestos
removal
- installation
of a sprinkler system
- renovation
of the ground (first) floor area to accommodate a new circulation desk
and offices, reserve reading collection, reserve reading room, the renovation
of two classrooms and collection management offices. In addition, library
administration (deans suite) will be relocated to the first floor
- painting,
new carpeting, rewiring, etc., is included
Dr.
Richard Wood
Dean of the Libraries
2/01/02
|